March 10, 20206 yr Author comment_496817 I have to omit the zones each time to set the alarm by User code + 6 then press 5,6,7 * then press easy set #+1 then this set the alarm. It will set alarm off if the PIR is obstructed. But once I do this or open door and enter the code. I have to manually do this process again! Any support would be appreciative. Link to comment https://www.thesecurityinstaller.co.uk/community/topic/43529-ademco-accord-8/page/4/#findComment-496817 Share on other sites Share on LinkedIn Share on X Share on Facebook {lang="reddit_text" Share via email Share on Pinterest More sharing options... Share this post
March 10, 20206 yr comment_496818 Those zones need programming out That's why omitting allows it to arm securitywarehouse Security Supplies from Security Warehouse Trade Members please contact us for your TSI vetted trade discount. Link to comment https://www.thesecurityinstaller.co.uk/community/topic/43529-ademco-accord-8/page/4/#findComment-496818 Share on other sites Share on LinkedIn Share on X Share on Facebook {lang="reddit_text" Share via email Share on Pinterest More sharing options... Share this post
March 10, 20206 yr comment_496819 You are manually omitting those circuits that's how it should work, omits are temporary. Permanent changes are done with programming or wiring them out. Link to comment https://www.thesecurityinstaller.co.uk/community/topic/43529-ademco-accord-8/page/4/#findComment-496819 Share on other sites Share on LinkedIn Share on X Share on Facebook {lang="reddit_text" Share via email Share on Pinterest More sharing options... Share this post
March 10, 20206 yr comment_496820 On 23/02/2020 at 17:48, PeterJames said: Have you tried linking out 5 6 and 7 ? If you have a multi meter then see if they are cc 18 minutes ago, Timmymeads said: I have to omit the zones each time to set the alarm by User code + 6 then press 5,6,7 * then press easy set #+1 then this set the alarm. It will set alarm off if the PIR is obstructed. But once I do this or open door and enter the code. I have to manually do this process again! Any support would be appreciative. You try the above yet? Link to comment https://www.thesecurityinstaller.co.uk/community/topic/43529-ademco-accord-8/page/4/#findComment-496820 Share on other sites Share on LinkedIn Share on X Share on Facebook {lang="reddit_text" Share via email Share on Pinterest More sharing options... Share this post
March 10, 20206 yr Author comment_496821 I have the programming code - How do it do it? Link to comment https://www.thesecurityinstaller.co.uk/community/topic/43529-ademco-accord-8/page/4/#findComment-496821 Share on other sites Share on LinkedIn Share on X Share on Facebook {lang="reddit_text" Share via email Share on Pinterest More sharing options... Share this post
March 10, 20206 yr comment_496825 1 hour ago, Timmymeads said: I have the programming code - How do it do it? Did you try what Peter James said? Link to comment https://www.thesecurityinstaller.co.uk/community/topic/43529-ademco-accord-8/page/4/#findComment-496825 Share on other sites Share on LinkedIn Share on X Share on Facebook {lang="reddit_text" Share via email Share on Pinterest More sharing options... Share this post
March 10, 20206 yr comment_496827 To be fair if you dont understand that much, its not a forum you need its an engineer. Linking out a wire across each circuit in the panel, take the existing wires out. Before you open the panel isolate the mains electricity can kill Link to comment https://www.thesecurityinstaller.co.uk/community/topic/43529-ademco-accord-8/page/4/#findComment-496827 Share on other sites Share on LinkedIn Share on X Share on Facebook {lang="reddit_text" Share via email Share on Pinterest More sharing options... Share this post
March 10, 20206 yr Author comment_496869 Yes I can link out and no how to do it just need to figure which wire is for which.l, I don’t have a multi meter but there might be instructions. I was more if I could do it through the panel system Link to comment https://www.thesecurityinstaller.co.uk/community/topic/43529-ademco-accord-8/page/4/#findComment-496869 Share on other sites Share on LinkedIn Share on X Share on Facebook {lang="reddit_text" Share via email Share on Pinterest More sharing options... Share this post
March 10, 20206 yr Author comment_496870 If I link out 5.6.7 zones then if I use easy set will it arm? Link to comment https://www.thesecurityinstaller.co.uk/community/topic/43529-ademco-accord-8/page/4/#findComment-496870 Share on other sites Share on LinkedIn Share on X Share on Facebook {lang="reddit_text" Share via email Share on Pinterest More sharing options... Share this post
March 10, 20206 yr comment_496874 44 minutes ago, Timmymeads said: If I link out 5.6.7 zones then if I use easy set will it arm? If it does then you know the problem is with the wiring if it doesnt the panel is probably knackered, tak a photo for ref before you start, remove existing wires because a short to tamper would also indicate open zone Link to comment https://www.thesecurityinstaller.co.uk/community/topic/43529-ademco-accord-8/page/4/#findComment-496874 Share on other sites Share on LinkedIn Share on X Share on Facebook {lang="reddit_text" Share via email Share on Pinterest More sharing options... Share this post